💻 techProduct7 views3 min read

What Happened to Advanced Arresting Gear (AAG)?

The Advanced Arresting Gear (AAG) is a state-of-the-art recovery system developed by General Atomics for the U.S. Navy's Gerald R. Ford-class aircraft carriers. Despite significant initial development challenges, cost overruns, and schedule delays, the AAG has demonstrated improved reliability and operational availability on the USS Gerald R. Ford (CVN-78) during its recent deployments, with further upgrades planned and deployment on subsequent Ford-class carriers underway.

Share:
⚡

Quick Answer

The Advanced Arresting Gear (AAG) is an electric motor-based system designed by General Atomics to replace the hydraulic arresting gear on U.S. Navy aircraft carriers, specifically the Ford-class. After facing significant developmental delays and cost increases due to technical complexities, AAG has demonstrated improved reliability on the USS Gerald R. Ford, achieving a high instantaneous operational availability rate of 0.987 during its second deployment in 2025-2026. The U.S. Navy is preparing a major reliability upgrade for AAG on the Ford in fiscal year 2029, including a fourth-engine solution, and is proceeding with its operational fielding on future carriers like CVN 79 (John F. Kennedy) in FY 2027, CVN 80 (Enterprise) in FY 2031, and CVN 81 (Doris Miller) in FY 2032.

📊Key Facts

RDT&E Costs (as of Oct 2015)
$743.5 million
DoD Inspector General Report, 2016
Cost Overrun vs. 2005 Plan (as of Oct 2015)
$571.5 million
DoD Inspector General Report, 2016
Total Fixed-Wing Aircraft Recoveries on USS Gerald R. Ford (since 2017 to March 2026)
36,863
U.S. Navy Modernized Selected Acquisition Report, April 2026
Instantaneous Operational Availability (first 6 months of Ford's second deployment, ending May 2026)
0.987
U.S. Navy Modernized Selected Acquisition Report, April 2026
Ford-class Carriers Planned for AAG
4 (CVN 78, 79, 80, 81)
U.S. Navy Modernized Selected Acquisition Report, April 2026

📅Complete Timeline16 events

1
July 2003Major

AAG Program Established

The U.S. Navy formally established the Advanced Arresting Gear (AAG) program to develop a new arresting system for its future aircraft carriers.

2
March 27, 2011Notable

First Inert Load Arrestment

The AAG system successfully conducted its first inert load arrestment at the Jet Car Track Site (JCTS) located at Joint Base McGuire–Dix–Lakehurst, New Jersey.

3
Early 2012Critical

Serious Water Twister Problems Discovered

Significant technical issues were identified with the AAG's 'water twisters,' critical components for energy absorption, leading to substantial development delays and cost increases.

4
October 2015Critical

RDT&E Costs Exceed Baselines

Research, Development, Test, and Evaluation (RDT&E) costs for the AAG program reached $743.5 million, exceeding the planned costs from the 2005 Acquisition Program Baseline by $571.5 million.

5
March 31, 2016Major

First F/A-18E Super Hornet Arrestment (Land-Based)

General Atomics and the U.S. Navy successfully conducted the first arrestment of an F/A-18E Super Hornet at the Runway Arrested Landing Site (RALS) at Joint Base McGuire–Dix–Lakehurst.

6
July 5, 2016Major

DoD IG Report Highlights Cost and Schedule Overruns

A DoD Inspector General report concluded that the AAG program exceeded its cost and schedule baselines due to technological immaturity and hardware failures.

7
2017Critical

Deployment on USS Gerald R. Ford (CVN-78)

The Advanced Arresting Gear was deployed on the USS Gerald R. Ford (CVN-78), the lead ship of the new Ford-class aircraft carriers.

8
January 30, 2020Major

Aircraft Compatibility Testing (ACT) Completed on CVN-78

The AAG system on USS Gerald R. Ford completed Aircraft Compatibility Testing, successfully recovering C-2A, E-2D+, EA-18G, and T-45C aircraft.

9
June-August 2021Notable

Full-Ship Shock Trials with No AAG Issues

The USS Gerald R. Ford conducted Full-Ship Shock Trials, a critical test of the ship's resilience, with no reported issues for the AAG system.

10
February 15, 2023Major

Over 12,500 Arrestments on CVN-78

As of this date, the AAG system had recovered over 12,577 fixed-wing aircraft aboard the USS Gerald R. Ford, demonstrating steadily improving performance.

11
June 2025Major

USS Gerald R. Ford Begins Second Deployment

The USS Gerald R. Ford commenced its second operational deployment, which would become a historic 11-month mission across multiple fleets.

12
March 2026Major

36,863 Total Aircraft Recoveries on CVN-78

By March 2026, the USS Gerald R. Ford had recovered a cumulative 36,863 fixed-wing aircraft since its commissioning, including 9,634 during its second deployment.

13
April 21, 2026Critical

High Operational Availability Reported

A U.S. Navy Modernized Selected Acquisition Report revealed that AAG achieved an instantaneous operational availability rate of 0.987 during the first six months of Ford's second deployment.

14
May 16, 2026Major

USS Gerald R. Ford Returns from Historic Deployment

The USS Gerald R. Ford and its strike group returned to Naval Station Norfolk after a historic 326-day deployment, showcasing the AAG's sustained performance.

15
Fiscal Year 2027Major

AAG Fielding on USS John F. Kennedy (CVN 79)

The U.S. Navy's April 2026 fielding plan identifies operational fielding for AAG on the USS John F. Kennedy (CVN 79).

16
Fiscal Year 2029Critical

Major Reliability Upgrade for CVN-78 AAG

A major reliability upgrade for the AAG aboard USS Gerald R. Ford (CVN 78) is expected, featuring a fourth-engine solution and other hardware/software improvements.

Follow this story

Get an email when this timeline gets a major update.

🔍Deep Dive Analysis

The Advanced Arresting Gear (AAG) was conceived by the U.S. Navy in July 2003 as a revolutionary replacement for the legacy Mark-7 (Mk-7) hydraulic arresting gear system used on Nimitz-class aircraft carriers. Developed by General Atomics, AAG was designed to offer significant advantages, including the ability to recover a broader range of aircraft, from the lightest unmanned aerial vehicles (UAVs) to the heaviest manned fighters, while simultaneously reducing maintenance demands and manpower requirements.

However, the development of AAG proved to be far more complex and challenging than initially anticipated. Early in 2012, serious technical problems emerged with the system's 'water twisters,' which are crucial for absorbing energy during an arrestment. These issues stemmed from an underestimation of the forces involved in the three-dimensional flow field within the twisters, leading to internal plate failures. This technical hurdle resulted in substantial delays, pushing back developmental testing by several years and significantly increasing research, development, test, and evaluation (RDT&E) costs. By October 2015, RDT&E costs had soared to $743.5 million, a staggering $571.5 million above the planned costs from the 2005 Acquisition Program Baseline.

Despite these setbacks, testing continued, with the first inert load arrestment occurring in March 2011 and the first fly-in arrestment of an F/A-18E Super Hornet at a land-based site in March 2016. The AAG was eventually deployed on the lead ship of the Ford-class, the USS Gerald R. Ford (CVN-78), in 2017. Initial operational periods on the Ford were met with scrutiny regarding the system's reliability and availability. However, through continuous hardware and software improvements, AAG's performance has steadily improved.

A key turning point came during the USS Gerald R. Ford's second operational deployment, which began in June 2025 and concluded in May 2026. During the first six months of this deployment, the AAG system achieved an instantaneous operational availability rate of 0.987, nearing the 0.985 threshold defined for system maturity. As of March 2026, the AAG on CVN-78 had successfully recovered 36,863 fixed-wing aircraft since the ship's commissioning in 2017, including 9,634 during its second deployment.

As of September 8, 2026, the AAG is operational on the USS Gerald R. Ford, demonstrating significantly improved performance and reliability. The U.S. Navy, in its April 2026 Modernized Selected Acquisition Report, detailed plans for a major reliability upgrade for AAG on CVN-78, expected to be fielded in fiscal year 2029. This upgrade will include an alternative fourth-engine solution and additional hardware and software enhancements, projected to improve reliability by an order of magnitude. Furthermore, AAG is slated for installation and operational fielding on subsequent Ford-class carriers: the USS John F. Kennedy (CVN 79) in fiscal year 2027, the USS Enterprise (CVN 80) in fiscal year 2031, and the USS Doris Miller (CVN 81) in fiscal year 2032. General Atomics continues to be the primary contractor for AAG production and associated systems.

What If...?

Explore alternate histories. What if Advanced Arresting Gear (AAG) made different choices?

Explore Scenarios
Building relationship map...

❓People Also Ask

What is the Advanced Arresting Gear (AAG)?
The Advanced Arresting Gear (AAG) is an advanced, electric motor-based system designed to safely recover aircraft landing on U.S. Navy aircraft carriers. It replaces older hydraulic systems, offering greater control and the ability to handle a wider range of aircraft types.
Which aircraft carriers use the AAG system?
Currently, the Advanced Arresting Gear is operational on the USS Gerald R. Ford (CVN-78). It is also planned for installation and operational fielding on future Ford-class carriers, including the USS John F. Kennedy (CVN 79), USS Enterprise (CVN 80), and USS Doris Miller (CVN 81).
What problems did AAG face during development?
AAG faced significant developmental challenges, primarily with its 'water twisters,' which are crucial for energy absorption. These technical issues led to hardware failures, software challenges, substantial cost overruns, and years of schedule delays.
What is the current status of AAG as of 2026?
As of September 2026, the AAG system is operational on the USS Gerald R. Ford and has demonstrated improved reliability, achieving a high instantaneous operational availability rate of 0.987 during its second deployment. The U.S. Navy plans a major reliability upgrade for CVN-78's AAG in fiscal year 2029.
Who manufactures the Advanced Arresting Gear?
The Advanced Arresting Gear (AAG) is developed and manufactured by General Atomics, an American energy and defense corporation specializing in advanced electromagnetic systems.