What Happened to Gigafactory New York?
Gigafactory New York, also known as Giga New York or Gigafactory 2, is a factory in Buffalo, New York, owned by the State of New York and leased by Tesla, Inc. Initially conceived under the "Buffalo Billion" initiative for solar panel production by SolarCity, the facility has faced controversies and shifts in focus. As of 2026, it primarily produces Tesla's conventional residential solar panels and Superchargers, and houses Autopilot data analysts, having recently met its long-standing job creation commitments.
Quick Answer
Gigafactory New York, a state-owned facility in Buffalo leased by Tesla, has evolved significantly since its inception. After initial struggles with Solar Roof production and the departure of partner Panasonic, the factory has successfully pivoted. As of early 2026, Tesla began shipping its own US-assembled residential solar panels (TSP-420) from the site, alongside continued production of Superchargers and Autopilot data labeling operations. The company also met its critical statewide job creation targets by the end of 2025, securing its future in the region despite past scrutiny.
📊Key Facts
📅Complete Timeline15 events
Buffalo Billion Initiative Announced
New York Governor Andrew Cuomo announces the 'Buffalo Billion' stimulus package, including plans for a high-tech manufacturing hub at the Riverbend site, targeting lighting manufacturer Soraa and solar panel manufacturer Silevo.
Construction Begins; SolarCity Acquires Silevo
Construction of the factory begins. SolarCity, founded by Elon Musk's cousins, acquires Silevo, becoming the primary intended tenant for the state-funded facility.
Tesla Acquires SolarCity
Tesla announces its acquisition of SolarCity for approximately $2.6 billion, bringing the Buffalo factory project under Tesla's umbrella.
Tesla Solar Roof Unveiled
Elon Musk unveils the Tesla Solar Roof, a key product intended for production at the Buffalo Gigafactory, predicting high production volumes.
Panasonic Partnership Finalized
Tesla and Panasonic finalize an agreement for Panasonic to manufacture photovoltaic (PV) cells and modules at the Buffalo factory.
Factory Completion and Initial Production
The Gigafactory New York construction is completed, and limited assembly of photovoltaic modules begins, with Tesla designating it as Gigafactory 2.
Buffalo Billion Corruption Convictions
A high-profile developer connected to the factory's construction is convicted of bid-rigging in the 'Buffalo Billion' corruption case, highlighting early controversies.
Panasonic Exits Solar Cell Manufacturing
Panasonic announces it will cease solar cell manufacturing operations at Gigafactory New York by September 2020, citing challenges in scaling production.
Shift to Supercharger and Autopilot Work
Following Panasonic's departure, Tesla pivots Gigafactory New York's operations to include the production of Superchargers and data labeling for its Autopilot software.
Allegations of Racism Emerge
Black employees at Gigafactory New York allege routine racist treatment by managers, including offensive remarks and being passed over for promotions.
New Lease Agreement Drafted
A new draft agreement between Tesla and New York State is reported, outlining increased job commitments (1,800 in Buffalo, 3,000 statewide) and higher rent payments through 2034.
Tesla Begins In-House Solar Panel Production
Tesla announces it has started producing its own new residential solar panels at Gigafactory New York, with first deliveries anticipated in Q1 2026.
Tesla Meets Job Creation Commitments
Tesla reports exceeding its statewide employment commitments with over 3,460 employees, including 2,399 at the Buffalo factory, avoiding substantial state penalties.
Launch of US-Made TSP-420 Solar Panel
Tesla launches its US-made 420-watt solar panel, the TSP-420, assembled at Gigafactory New York, marking its first fully designed and manufactured panel.
Solar Roof Discontinuation
Tesla informs third-party installers that it will no longer supply Solar Roof tiles for new projects, effectively discontinuing the product and shifting focus to conventional solar panels.
Follow this story
Get an email when this timeline gets a major update.
🔍Deep Dive Analysis
Gigafactory New York, officially known as Gigafactory 2, is a sprawling 1.2 million sq ft facility in Buffalo, New York, built on a remediated brownfield site that once housed a steel mill. Its origins trace back to New York Governor Andrew Cuomo's ambitious "Buffalo Billion" stimulus package, announced in 2013, which aimed to revitalize the region with high-tech manufacturing jobs. The state committed significant funds, eventually totaling around $959 million, to construct and equip the factory, which would then be leased to a private company for a nominal fee.
Construction began in September 2014, with SolarCity, a solar energy company founded by Elon Musk's cousins and later acquired by Tesla, becoming the primary tenant after purchasing original tenant Silevo. The vision was to create the largest solar plant in the U.S., producing up to 1 gigawatt of solar panels annually by 2019. However, the project was plagued by delays, controversies, and criticisms from its early days, including allegations of inflated job promises, cost overruns, and a bid-rigging scandal involving state officials in 2018.
Following Tesla's acquisition of SolarCity in 2016, the factory's focus shifted to the highly anticipated Tesla Solar Roof tiles. In December 2016, Panasonic partnered with Tesla to manufacture photovoltaic cells and modules at the Buffalo factory, with production of the first PV modules beginning in summer 2017. Despite Elon Musk's ambitious predictions of producing 1,000 Solar Roofs weekly, commercial production of the shingles didn't start until March 2020, and the product proved challenging to scale. Panasonic ultimately decided to exit the solar cell manufacturing partnership in Buffalo by September 2020, leaving Tesla to operate the factory alone.
In the wake of Panasonic's departure and ongoing scrutiny over job creation commitments, Tesla diversified the factory's activities. It began producing Superchargers and employing data analysts for its Autopilot software at the site. The company received multiple extensions to meet its job targets, which were tied to significant financial penalties if not met. By the end of 2025, Tesla reported a statewide headcount exceeding 3,460 employees, including 2,399 full-time workers at the Buffalo factory, thereby fulfilling its commitments to New York State. This achievement secured the factory's future, with a new lease agreement drafted in 2024 that could run through 2034, increasing job requirements and rent payments.
A significant development in late 2025 and early 2026 was Tesla's renewed focus on its solar business, specifically the in-house production of conventional residential solar panels. In October 2025, Tesla announced it had started producing its own new solar panel at Gigafactory New York, with first deliveries expected in Q1 2026. In January 2026, Tesla launched a US-made 420-watt solar panel (TSP-420) assembled at the Buffalo plant, marking its first fully designed and manufactured solar panel. This pivot came as Tesla quietly discontinued its Solar Roof tile product in August 2026, informing third-party installers it would no longer supply the tiles and redirecting customers to conventional solar panels. The Buffalo facility's current solar panel production capacity is a modest 300 MW per year, with plans for larger-scale solar panel manufacturing in Texas. Despite past controversies and the end of the Solar Roof, Gigafactory New York continues to be a key site for Tesla's energy and AI initiatives, employing thousands and contributing to the company's evolving sustainable energy strategy.
What If...?
Explore alternate histories. What if Gigafactory New York made different choices?